starclick


New poultry farm establishment & Existing farm section

 PLANING

The farm are captured based on the expansion plan received form the D.G.M  to branch manager .

PARAMETER OF THE NEW FARM  SELECTION 

The area to be isolated i.e away  form the residential area.

There to be not be any broiler commercial  farms nearby .

CONTROL/QUALITY PARAMETER

Cage shed -1 km away form the village .

There should not be any development for about 10 to 15 years .

Deep litter -1 km  away form the village.

The road to be good condition for passage of heavy trucks.

The  water availability ,quality  and quantity to be good in the surrounding area.

The L.S to be collect the water sample in the sterilised  water  container and take  them to  the regional lab  for lab testing .

The lab report  is given to the branch manager through mail stating whether  it is  accepted / not accepted.

CONTROL/QUALITY PARAMETER

Quantity -1 litter/birds /day

pH-6.5-7.5

Hardness -400 and below.

The LS to identify the behaviour of the farmer why talking with him.once all these parameters are ok then the DGM along with the manager has to be visit the form and verify all those above satisfied parameter are good.the decision to verify all the terms and condition on service charges to the farmer. Finally all these reports are completed to the decision and then he has to across check and only needed basic he also need to visit the land.

TRI PARTY AGRIMENT 

The farmer to be communicate with the branch manager through phone and finally the date and time of meeting with the DGM and branch manager for signing the agreement.one the day of signing the agreement process farmer to bring the following documents to the office.

1-title deed 

2-VAO certificate 

3-address proof ration card

4-electric city bill

5-land tax receipt

Partnership form net partnership deed xerox. Bank details required.

the document are verified and if it is OK then the agreement is signed by the farmer and DGM and it is sent to the bank.the confirmation letter stating the request for the issue of loan is given to the bank with the signature of the DGM. The farmer 2 to approach the branch periodically for the receipt of the loan.

START OF THE CONSTRUCTION PROCESS

When the loan get section the former to communicate with the branch manager through phone and canal is the date and time of visit by branch manager to the new farm. The BM to educate the farmer about the guideline for the contraction of said to the time of visit.

THE GUIDELINES TO INCLUDE THE FOLLOWING

SAID TO BE IN EAST WEST DIRECTION LAND SOLD BE IN SUCH A WAY THAT THE EAST WEST ORIENTATION SHOULD BE LONG.

Farm should  have its  own  bore water.

The minimum words 10,000 to maximum 30,000 with 12 % to 15% additional square feet. Feed for other structures and amenities.

The gap in between the said is 75 and hundred feet minimum. Cage partition should be 200 feet. Egg cleaning room-200 square feet for 10000 birds. Set the platform flooring cement concrete. Shed pillar height to be 10 feet above the platform. Pillar to pillar distance  at side should be less than 15 feet. Set both side solvi copper with 1 inch chain link without gap the bottom of the kids also should be cover with chain link for fishnet. Plan platform to cage should be fixed with chain link or barbed  where to prevent Birds felling down.

Sintex tank capacity 2000 litre per sed height of minimum 8 feet from the platform.overhead tank capacity 1 litre for 1 birds per day. Sump tank capacity 1 litre for birds minimum. Size of the pipeline for connecting overhead tank to sintex tank overhead half inch pipeline. Size of pipeline for connecting sintex tank to set tank 1 inch. EB 40 KB minimum for 10000 birds.for every CFL bulb /tubelight 40 watts for 160 square feet. Dropping holder 338 have gaps on each platform if CFL is provided. Tubelight mean it should be fixed on it 4 feet above cages. Street light is provided on either side East and West of the alternate shed. Good fencing with chain link dog broke and man gate.Michaels entry with spray breath 10 feet length 16 feet and women entry get with humans to breath 3 feet height 6 feet length 6 feet. vehicle dip and foot dip to be provided at the main gate. One security watch cabin with open view in contructed at the main gate. 1 visitors bathroom is provided near men gate. Disposal kit with cover for disposing dead birds. Menu dropping area a way that said minimum hundred feets. Drainage to avoid stranant  of water inside the poultry premise.number of labour quarters 10 to 12 and to staff quarters for 20000 its capacity. Female cage boxes 18 inches 18 inches with bottom 1.5 and 2.5 inches. 3 door wide open 6.527 inches and the model to be filled by farm. Meals cage boxes 24 inches 18 inches depth 24 inches height bottom 1.5 to 1.5 inches. Each side tank 10 litre capacity needed.the cage box side partition should have opening of 6 inches at nipple classing area nipples should be placed at positional only. Each cage partition should be maximum 250 length. Fan previous  air circulating fan to 200 and 250 birds equal distributed. D Pharma to start the construction process of the said and complete it within 6 month of the agreement process and the branch manager to visit the form on in 15 days during the construction process. Chain link fencing to be done before the start of the contraction process of the shed. This said to be clean 2 week before the birds arrival. Then arrange the reader drinker and place the allotted what's in the news shed. The cage form are capture based on the the expansion plan received from the divisional head to the branch manager.the bank branch manager to identify the previous performance of the learner by their production performance. Honours co-operation with our company. Theft incidents. Disease outbreak. Integration issues.If the branch manager is satisfied the previous performance of the farmer then he has to tell him about the policy of our company next week he agrees then the company proceed to half tie up. Before placing the birds divisional head sold this cuss him about the previous performance and find out the definite difficulties of birth side 2 to rectify and get the good productivity. Quantity need 1 litre per words par day. PH 6.5 and hardness 600 and below.